Southern African Renewable and Alternative Energy Association (SAAEA)
  • Home
  • ABOUT US
    • Services
    • Advertise with us....
    • Our Partners
    • Privacy Policy
  • MEMBERS
    • Members
    • Membership Benefits
  • News
  • Tenders
  • Technologies
    • Wind
    • Solar PV
    • Solar CSP
    • Solar Water Heating
    • Hydro
    • Biogas
    • Biomass
    • Waste to Energy
    • Fuel Cells
    • Batteries
  • FUNDING
  • Events Calendar
  • Contact Us

Mantashe confirms some RMIPPPP projects won’t close, outlines six-monthly renewables procurement tempo

2/15/2022

0 Comments

 
Picture
Mineral Resources and Energy Minister Gwede Mantashe confirmed on Tuesday that not all of the 11 Risk Mitigation Independent Power Producer Procurement Programme (RMIPPPP) preferred bidders would be in a position to conclude power purchase agreements (PPAs) at the end of March, the deadline for the projects to reach financial close.

During a Parliamentary debate on President Cyril Ramaphosa’s recent State of the Nation Address (SoNA), Mantashe said steps were being taken to address a current supply shortfall that the President estimated to be 4 000 MW, but which several commentators believe to be closer to 6 000 MW.

He said PPAs would be signed next month with RMIPPPP preferred bidders, which were selected as part of an emergency, albeit much delayed, procurement round for 2 000 MW.

The projects were selected in March last year and the initial financial close deadline of July was extended initially to the end of September, then to January this year and finally to the end of March.

“The challenge is that not all of the RMIPPPP preferred bidder projects may be in a position to conclude power purchase agreements due to outstanding processes on their side,” Mantashe told lawmakers.

His statement gels with the one made by Ramaphosa in his SoNA speech, in which the President announced that only 800 MW of the 2 000 MW in projects selected under the RMIPPPP were ready to proceed.
Advert

Picture
Given that three Karpowership projects comprised about 1 200 MW of the RMIPPPP allocation, there was immediate speculation that the projects, which face legal, environmental and gas-pricing uncertainty, were among those that were not ready to proceed.

Mantashe also announced that 2 600 MW of renewable energy being procured under Bid Window 5 of the Renewable Energy Independent Power Producer Procurement Programme would enter into PPAs in April and announced that Bid Window 6 for another 2 600 MW of wind and solar would be launched at the end of March.

“Thereafter, additional bid windows, including Bid Window 7, will follow at six-month intervals.”

Read more........
0 Comments

Scatec awarded 540 MW solar plant with storage in a government tender in South Africa

6/2/2021

0 Comments

 
Picture
Oslo, 1 June 2021: Scatec has today been awarded Preferred Bidder status on three projects totaling 150MW (3x50MW) of Contracted Capacity, by the Department of Mineral Resources and Energy in South Africa under the technology agnostic Risk Mitigation Power Procurement Programme (RMIPPP). The tariffs awarded to the projects fall within the range of the previously awarded preferred bidders.

The three projects (Kenhardt 1-3), in total consisting of 540 MW solar and 225 MW/1,140 MWh battery storage, were bid based on sites located in the sundrenched Northern Cape Province of South Africa. The projects awarded to Scatec are the only projects with preferred bidders status exclusivity making use of renewable energy technology, making it arguably one of the largest single site solar + storage hybrids in the world.

“This is truly a great milestone for Scatec and renewable energy. We are demonstrating that cost competitive dispatchable solar power can be delivered at large scale with short implementation time. This confirms that renewable energy is an ideal choice for driving electricity generation growth in Africa and other developing countries”, says CEO Raymond Carlsen.

The solar and storage solution will provide dispatchable power from 5:00 am in the morning to 21:30 at night and will deliver much needed power to the South African economy. The power will be sold under a 20-year Power Purchase Agreement with a paid capacity charge.

Financing has already been sourced as part of the bidding process. Project capex is estimated to be USD 1 billion and will be funded by project finance debt from a consortium of commercial banks and Development Finance Institutions with expected debt leverage of 80%. Scatec will own 51 % of the equity in the project with H1 Holdings, our local Black Economic Empowerment partner owning 49%. Scatec will be the Engineering, Procurement and Construction (EPC) provider and provide Operation & Maintenance as well as Asset Management services to the power plants.

Advert
Picture
​Financial close is expected later in 2021 with grid connection by the end of 2022.
“This award further cements Scatec’s position as the leading solar IPP in South Africa and on the African continent. To date, we have successfully completed six solar plants under the country’s well known REIPPP programme and employ more than 200 people, which is set to grow further. With Round 5 of REIPPP launched in April, we are looking forward to further building on this solid foundation and experience from successful solar projects and add other renewable technologies to our portfolio”, says Carlsen.
Scatec’s integrated technology approach strengthens the competitiveness of renewables and expands the market potential. The company sees significant opportunities within hybrid solutions and is currently working on developing several projects using solar and batteries to create firm renewable power; and also combining solar with hydro to increase value proposition and competitiveness of hydro. In addition, Scatec works with partners to combine competitive renewable energy with industrial projects. In total, about 15 percent of the company’s project pipeline consists of hybrid solutions projects.
For further information, please contact:
Mikkel Tørud, CFO, tel: +47 976 99 144, ir@scatec.com
Ingrid Aarsnes, VP Communication & IR, tel: +47 950 38 364, ingrid.aarsnes@scatec.com
0 Comments

Mantashe has left South African Independent Power Producers out in the cold, and we’re giving up

5/31/2021

0 Comments

 
Picture
After five years of research, development and being ‘shovel ready’, locally-owned renewable energy companies have been effectively frozen out by Gwede Mantashe’s latest procurement announcement. Local Independent Power Producers have been left with stranded projects and five years of costs in keeping them ‘construction ready’ at the government’s request.

Minister of Mineral Resources and Energy Gwede Mantashe recently announced a raft of measures aimed at resurrecting the ailing state procurement of renewable energy. However, in a glaring omission, he failed to mention any intention to progress with a set of fully developed and awarded renewable energy projects representing 100MW of locally developed capacity, still awaiting Eskom’s signature.

Now instead of progressing with the projects that have been kept “shovel ready” for five years, he appears to prioritise the awarding of “emergency” projects to foreign-led entities such as those hailing from Turkey and Saudi Arabia.

The Small Projects Programme (SPP) was established in 2013 through the Department of Energy (DoE), in parallel to the conventional Renewable Energy Independent Power Producers Procurement Programme (REIPPPP). It was facilitated by the Independent Power Producers (IPP) office to award projects up to 5MW in size with the stated objective “to allow South African citizens who are, or who own or control, SMEs and or emerging, smaller power developers an opportunity to participate in the Renewable Energy generation sector”.

The high development and capital costs for large infrastructure projects make it difficult for local entities without experience to raise the funding and attract the financial, legal and technical support required for projects of scale. As a consequence, the larger REIPPPP programme, aimed at projects between 75MW and 140MW, has been dominated by international utility companies. The result is that, despite billions of rands of IPP projects being procured, we have almost no local IPP companies able to compete with large foreign utilities representing, for example, the Eskom equivalents of Norway, Italy, France and Saudi Arabia.

Those within Treasury, DoE and the IPP office who understood the importance of establishing local skills and experience, promoted the Small Projects Programme, which was officially launched in the form of a Request for Proposals in August 2013. Prospective bidders were asked to submit projects of up to 5MW in size.  In contrast to the larger REIPPPP, this process mandated higher levels of local ownership, with a specific requirement that 60% of the proposed project ownership had to eventually be held by a South African parent company.

The bid requirements were otherwise substantially similar to the large IPP programme, making submissions time-consuming and costly. All land, grid, environmental and permitting rights needed to be secured and advanced to qualify for evaluation. The costs, amounting to several hundred thousand rands per project, were incurred by local developers seeking to respond to the government’s request for proposals.

In 2015, after two rounds of bidding, the IPP office awarded preferred bidder status to 20 projects ranging across wind, solar and biomass technologies, and representing around 100MW in capacity. The projects were instructed to develop further and prepare for financial close and signature of Power Purchase Agreements (PPAs) with Eskom.

Advert
Picture
Since then, after five years of incurring costs to keep the projects on standby for government go-ahead, no PPAs have been signed and no projects have proceeded into construction.

Rather than give a clear message that the state is not proceeding with these projects, the preferred bidder status was renewed by the IPP office no less than six times during the five-year period, leaving companies guessing as to the government’s intent.

In 2020, at the government’s request, and in good faith to South African consumers, the bidders adjusted their tariffs downwards to account for improvements in capital costs over the years of delay. Eight months after the adjusted tariffs were submitted, there is still no progress. Many of the locally owned companies that were investing in developing smaller projects for this process have now put down tools and given up on their projects, due to the lack of government progress and commitment.

Read more........
0 Comments

IPP Bid Window 5 now available

4/14/2021

0 Comments

 
Picture
0 Comments

​REIPPPP Bid Window 5: Delayed release of RFP

4/9/2021

1 Comment

 
Picture
The Department of Mineral Resources and Energy (DMRE) have announced a delay in the release of documentation for the Request for Proposal (RFP) for the Renewable Energy IPP Procurement Programme (REIPPPP) Bid Window 5.
The delay is as a result of a need to align certain parts of the RFP documents with the feedback from National Treasury on the PPPFA exemption application.
Government remains committed to the urgent procurement of the much-needed energy to power our economic recovery.
We are working in earnest to ensure that this delay does not negatively affect the timelines we have set out to get these projects connected to the grid.
The Department intends to release the documentation for BW 5 RFP not later than 12 April 2021.

1 Comment

Power Shift: Draft ministerial determinations propose 13,813 MW of new-build by IPPs — none by Eskom

3/23/2020

0 Comments

 
Picture
Two so-called draft “S34 determinations” by the National Energy Regulator of South Africa (Nersa) are the first step in the process of procurement of new electricity generation capacity in South Africa totalling some 13,813 MW from independent power producers (IPPs).
​ 
South Africa’s national energy regulator on Friday published two draft determinations by Minerals and Energy Minister Gwede Mantashe in terms of Section 34 (1) of the Electricity Regulation Act.

The first draft S34 determination relates to the procurement of 2,000 MW of new generation capacity between 2019 and 2022, and the second draft S34 determination to the procurement of a further 11,813 MW between 2022 and 2027. 

These draft S34 determinations begin the procurement process after the gazetting of the South African national integrated resource plan for electricity, IRP 2019 on 18 November 2019. The determinations were submitted to Nersa by the minister on 21 February 2020 for “concurrence” by the energy regulator and published on Friday 20 March 2020.

A high court judgment in April 2017 ruled that in terms of the Electricity Regulation Act and the Promotion of Administrative Justice Act (PAJA), Nersa is required to concur with the draft determinations following a public consultation process before they become final and are gazetted. 

The public consultation process began after Nersa published two consultation papers on 18 March 2020. These call for public comment and input on the two draft S34 determinations issued by Minister Mantashe, by 14 April 2020 and 7 May 2020 respectively.

Advertisement
Picture
​Despite the current electricity supply emergency, which has resulted in up to Stage 6 (6,000 MW) load shedding in South Africa, Nersa has indicated that now, more than a month since receiving the draft S34 determinations, it will require a further three months to concur with the first S34 determination, and six months for the second.

Nersa does not seem to have got the message from Minister Mantashe when he said recently:

“Officials in the department are used to working according to rules, where it takes three months to do this, or six months to do that. The situation we are in requires a change of approach. That’s why we are engaging with Nersa and everybody to say: Guys, let’s accelerate processes, because if we don’t, we are going to be plunged into darkness.”

The Department of Minerals and Energy and Nersa are coming under increasing pressure and criticism for the snail’s pace of their bureaucratic processes and decisions. The energy regulator refutes this criticism and says that “Nersa is cognisant of the urgency of the request [for concurrence] as evidenced by the proposed fast-tracked concurrence process in the consultation papers”.

The draft S34 determinations indicate that electricity produced from the new generation capacity will be procured from IPPs “through one or more tendering procedures which are fair, transparent, competitive and cost-effective”.

The electricity procured from IPPs by the department in terms of the draft S34 determinations may only be sold to Eskom as the designated buyer of the electricity, in accordance with power purchase agreements (PPAs) concluded in the course of the procurement programmes.

Recent statements by the ministers of public enterprises and minerals and energy have indicated that Eskom should not be excluded from building, owning and operating new renewable energy generation capacity. However, the draft Section 34 determinations indicate that all new generation capacity up to 2027 – wind, solar, energy storage, gas and coal-fired – will come from IPPs. None of the new generation capacity will come from Eskom itself. 

This is a big shift from the current Eskom monopoly, towards a more diversified electricity supply industry. It also represents a significant diversification away from South Africa’s over-dependence on coal as primary energy for power generation, which stands at about 80% of the total electricity generated in South Africa. 

Chris Yelland is MD of EE Business Intelligence.
0 Comments

Nersa moves to source electricity from private providers

3/20/2020

0 Comments

 
Picture
Energy regulator Nersa took a crucial step toward allowing the government to procure emergency power and to allow the building of more privately owned power plants.

The regulator issued public consultation papers after the energy minister allowed the procurement of 2GW of emergency capacity as soon as possible and the construction of 6.GW of capacity from longer-term renewable power plants. The longer-term plan is in line with a government energy framework that includes additional generation capacity in the form of non-renewable power. South Africa is in urgent need of more electricity to end recurrent outages.

As soon as the process is finished by the regulator, procurement of new capacity can begin, department of mineral resources & energy deputy director-general Jacob Mbele said on 3 March.

Advertisement
Picture
The deadline for comment on the framework for the procurement of emergency power is 14 April and the process will be completed in three months. The deadline for the longer-term plants, which encompass a range of technologies from wind to battery storage and coal, will close on 7 May and the process will be finalised after about six months, the documents said.  — Reported by Antony Sguazzin and Paul Burkhardt, (c) 2020 Bloomberg LP

​Source......
0 Comments

Emergency power for South Africa – Details

2/20/2020

0 Comments

 
Picture
South Africa received hundreds of responses to a call for 3,000 megawatts of emergency power that it estimates could be brought online within two years.
The Department of Mineral Resources and Energy put out a request for information in December to gather solutions for power generation in the midst of outages that are slowing economic growth.


There were 481 responses to the RFI that included options for gas, liquid fuels, coal, renewables, storage and nuclear, Mineral Resources and Energy Minister Gwede Mantashe told lawmakers Wednesday.

A preliminary analysis found that “some proposals can bring power to the grid in less than 24 months,” Mantashe said. The original request asked for short-term power-supply options of as much as 3,000 megawatts within a year.

Analysis by the department “also suggests that longer-term contracting is required to ensure prices do not negatively affect the current tariffs.”

The National Energy Regulator of South Africa also received 132 applications for a total capacity of 59 megawatts of generation for own use, according to Mantashe.

The licensing requirements for this category have been removed in an effort to reduce South Africa’s power supply deficit.
​
Source.....

0 Comments

Engineers call for restarting of ‘successful’ IPP programme to address power crisis - RSA

1/30/2020

0 Comments

 
Picture
Consulting Engineers South Africa (CESA) president Sugen Pillay urged government on Wednesday to urgently restart its “successful” renewable-energy procurement programme to help address the country’s prevailing electricity crisis.

Briefing the media in Johannesburg, Pillay said CESA was particularly keen for the fifth bid window of the Renewable Energy Independent Power Producer Procurement Programme (REIPPPP) to be initiated, as the REIPPPP was a stand-out example of a public procurement scheme that had worked.

“In addition to its value as a short-term intervention towards addressing our electricity crisis, it will also inject, albeit small, much-needed project opportunities for consulting engineers and contractors,” he added.

The Integrated Resource Plan 2019 (IRP 2019), which was published in October, calls for 1 600 MW of wind and 1 000 MW of solar photovoltaic (PV) capacity to be added in most years between 2020 and 2030, translating to the addition of more than 17 000 MW of new wind and 8 200 MW of new solar PV (excluding embedded generation) capacity in ten years.

For procurement to be initiated, however, Mineral Resources and Energy Minister Gwede Mantashe needs to publish Ministerial determinations in line with Section 34 of the Electricity Regulation Act and to do so with the concurrence of the National Energy Regulator of South Africa.

Advertisement
Picture
To date, Mantashe has not published the document, with the Department of Mineral Resources and Energy (DMRE) instead focusing on a Risk Mitigation Power Procurement Programme, the implementation of which will be guided by responses to a request for information (RFI) on short-term supply and demand options.

The DMRE had given itself a month from the January 31 RFI closing date to evaluate the responses and develop a procurement programme or programmes.

Read more......
0 Comments

Acting IPP Office head promises ‘extensive' talks with stakeholders on new bid documents

8/19/2019

0 Comments

 
Picture
The acting head of the Independent Power Producer Office (IPPO), Advocate Sandra Coetzee, has indicated that there should be “no surprises” in the bid documentation that will be released once procurement activities resume again, following a hiatus of nearly five years.

Coetzee, who stepped into the role in late July following the departure of Karen Breytenbach, tells Engineering News Online it is premature to offer detailed insight into the changes being considered. She confirms, however, that these adjustments will be guided by the principles of greater inclusivity and transformation, as well as affordability.

“With regard to procurement design, the team has done a considerable amount of work that is putting us in a good position for procurement as soon as determinations are in place after promulgation of the IRP.  We are actively engaging with our colleagues at the Department of Mineral Resources and Energy (DMRE) in this process."

The IPPO also intends having an “extensive” series of stakeholder engagements ahead of the release of the documentation to ensure the bankability of programmes and that they remain attractive to potential independent power producer (IPP) investors. These engagements will be initiated once the Integrated Resource Plan (IRP) is published.

“The roll-out of the programme will continue to build on the strong foundations of the past nine years,” Coetzee insists, describing those foundations as being a predictable regulatory framework, as well as proving investors with the certainty of lawful and compliant procurement.

Through the IPPO’s flagship Renewable Energy Independent Power Producer Procurement Programme (REIPPPP) 6 323 MW of mostly solar and wind capacity has been procured since 2011 across 92 separate projects, spurring about R200-billion in investment.

Advertisement
Picture
Coetzee’s immediate priority is to ensure that the IPPO is ready to implement any procurement programmes that will arise once the IRP is promulgated and the Ministerial determinations are published. With the energy sector being in crisis, the role of a capable and ready IPPO is important to attract urgently needed investment in generation capacity in South Africa.

Coetzee has deep knowledge and rich experience in infrastructure development in South Africa and across the continent. She also has senior management experience in government and the public sector having previously worked at the Department of Public Enterprises and South African Airways.

Read more....
0 Comments
<<Previous
    Picture
    Picture

    Tender Alerts
    ​

    Tenders available to Gold Members....

    Categories

    All
    Air Conditioning
    Algae
    Alternative Energy
    Battery
    Battery Backup
    Bioenergy
    Biofuel
    Biogas
    Biomass
    Blockchain
    Business Opurtunities
    Carbon Credits
    Carbon Footprint
    Carbon Tax
    Carbon Trading
    Clean Cook Stoves
    Climate Change
    Cogeneration
    Concentrated Solar Power
    Cpv
    Csp
    Demand Side Management
    Desalination
    Distributed Generation
    Electric Vehicles
    Embedded Generation
    Employment
    Employment Wanted
    Energy Efficiency
    Energy Management
    Energy Storage
    Eskom
    Events
    Events And Conferences
    FreedomCor
    FSAAEA
    Fuel Cells
    Funding
    Funding For Renewables
    Funnies
    Gas
    Gas Generation
    Gas To Liquids
    Gas To Power
    Generators
    Green Building
    Green Cities
    Heat Recovery
    Hydrogen
    Hydro Power
    Independant Power Producer
    Integrated Resource Plan
    Inverters
    Ipp
    Irp
    Kinetic Energy
    Landfill Gas
    Led Lighting
    LiFePO4
    Load Shedding
    Member Profiles
    Members
    Member Updates
    Methane
    Microgrid
    Mini Grids
    Miscanthus
    MSAAEA
    Nersa
    Net Metering
    News Africa
    News Global
    News South Africa
    News UK
    News USA
    Nuclear
    Ocean Power
    Our Partners
    Our Social Responsibility
    Pay As You Go Solar
    Power Purchase Agreement
    Power Ship
    Ppa
    Pv Mounting Systems
    Reipppp
    Renewable Energy
    Renewable Energy Events
    Renewable-energy-tax-incentives
    Renewables
    Renewables South Africa
    Risk Management
    Rooftop Pv
    SAAEA
    Shale Gas
    Small Project Ipp
    Solar Aircon
    Solar Farm
    Solar Power
    Solar Pv
    Solar Water Heating
    Solar Water Heating Swh6206859afc
    South Africa
    Specials
    Sustainable Development
    SWH
    Technologies
    Tenders
    Tenders For Renewable Energy
    Tesla
    Thin Film Pv
    Training
    Tyre Depolymerisation
    Tyre Recycling
    Ups
    Waste To Energy
    Water
    Wave Power
    Wind Farm
    Wind Measurement
    Wind Power
    Yingli

    RSS Feed

    See older posts...

    View my profile on LinkedIn
Powered by Create your own unique website with customizable templates.